HELPING TO RESTORE HONING LOCK
Sunday January 25 2004
From 0930hrs to 1530hrs
On Sunday January 25 2004 a group of members from the
Ipswich Branch of the IWA went to Honing lock on the North Walsham and
Dilham Canal to assist The East Anglian Waterways Association with some
restoration work at Honing Lock on the Dilham Canal.
The North Walsham and Dilham Canal runs along the River Ant from just
above Wayford Bridge to Antingham ponds which are just North of North
Walsham. It was built to carry grain and flour to and from the mills
by wherry. Honing lock is the first lock on the canal.
![]() Frost on the ground as we set up the tea table |
Sunday was a very bright morning with quite a bit of frost on the ground. 30 of us gathered at the lock side around 9.30, some members of the Ipswich IWA and some members of the East Anglian Waterways Association and a few members of both. I had visited the lock a couple of weeks earlier for a look round and to take a few photos, so this site contains some before and after shots.
|
|||
|
The first job tackled was to remove a long low tree branch in the car parking area, this gives room for two more cars to park on reasonably firm ground. Unfortunately this area was still not available for us to use as there was a large bag of sand left there for filling sandbags and we had to leave our cars up by the old railway bridge and walk down Weavers Way to the lock.
|
||||
|
|
There were three main tasks for the day. The major one of these was to remove two large tree stumps that were growing down the back of the lock wall on the west side.
|
|||
|
The second was to use the large bag of sand that had been delivered to the car cark to make sandbags. These were to be used to dam the water in the dyke to facilitate building a bridge to allow vehicle access to the lock side.
|
||||
|
The third was to clear undergrowth from the canal side
up stream of the lock so
|
||||
|
After we had unloaded all the equipment and carried/wheel barrowed it to the work site we set to, forming ourselves into 4 work groups. One group made a start clearing the west canal bank above the lock and lighting a fire to burn all the scrub that was removed, unfortunately the smoke from this slowly drifted across the canal to where the second group were clearing the east bank. (I was in the second group.) The work on the west bank was mainly cutting back Alders to give a 6 foot wide path along the side of the canal. This progressed quite rapidly for about the first 40 to 50 yards after which the chain saw was called in to remove some of the larger timber.
|
||||
|
On the east bank the first obstacle was a good sized patch of brambles directly behind the Environment Agency's water level monitoring box. It was just beyond here where its planned to put an overspill weir between the canal and the dyke to control the water level after the gates are installed. The whole area between the canal and the back dyke had to be cleared for about 10 yards. After the brambles it was into the young willows that had grown up from the root stocks that had been cut back in previous years. By the end of the day we had both cleared a good section of the bank, further on the east side that the west as the going got much easier the further we went.
|
|
|||
![]() Diana showing the size of the stumps |
Another team set to on the two large roots growing in
behind the lock walls, luckily the only damage they had caused to the
structure of the lock was lifting the concrete coping from the top of
the walls. At one point the concrete was well imbedded into the timber
and remained there after the stump was removed.
|
![]() The strain is on the Tirfor as they continue to hack away the roots |
||
|
The final team started the day filling sandbags from the bulk bag of sand that had been delivered earlier in the week. These were then transported by wheelbarrow and used to form a coffer dam along one side of the dyke just by the foundations for the foot bridge. These footings are going to be enlarged so that a bridge capable of carrying a truck can be put across the dyke. This will allow diggers, dumpers etc access to the lock side and canal bank to construct the weir and continue with the lock restoration.
|
||||
|
During
the course of the day we had a few breaks for tea, we were able to boil
the water with a couple of electric kettles and the generator that we
had on site. Kettle boiling was controlled by the chairman of the
Ipswich IWA who can be seen in his green overalls smoking his
pipe, in red is Di who was serving the teas.
|
||||
|
|
||||
|
One other small but essential job was carried out and that was to erect an information board on the foot bridge that crosses the head of the lock which has a map of the navigation and also a potted history.
Click the information board to see more photos of the lock area Click HERE to return to Local Waterways
|